Commercial & Industrial Flooring

How Long Does Commercial Resin Flooring Take to Install? Warehouse & Factory Downtime Explained

For a business considering a new resin floor, installation time can be just as important as price.

A warehouse may have deliveries moving every day. A factory may have production schedules to maintain. Workshops, commercial units and distribution facilities may not be able to simply stop operating for an extended period.

So one of the most important questions to ask before a commercial flooring project is:

How long will the area need to be out of use?

There isn’t one installation time that applies to every resin floor.

The answer depends on the condition of the existing floor, preparation required, repairs, flooring system, number of stages, site conditions and how the building operates.

In this guide, Epoxy Guys explains what can affect commercial resin flooring installation time and how businesses can start planning around downtime.

Why can’t commercial resin flooring have one standard installation time?

Because the resin application is only one part of the project.

Before the finished floor can return to service, a project may involve:

  • Clearing and accessing the area
  • Mechanical floor preparation
  • Removal of unsuitable existing coatings
  • Cleaning
  • Concrete repairs
  • Additional substrate preparation where required
  • Priming
  • Resin application
  • Additional coats or system layers
  • Finishing stages
  • Curing
  • Inspection before the area returns to normal use

Not every project requires every stage.

However, quoting an installation time based solely on floor area can overlook much of the work involved. The full sequence is set out in our commercial installation process.

Floor condition can affect the programme

Two warehouses of the same size can have completely different installation programmes.

One may have relatively sound concrete requiring straightforward preparation.

Another may contain cracks, damaged sections, old coatings or contamination that need to be addressed before the flooring system is installed.

The condition of the existing substrate therefore needs to be considered when planning the project.

If your existing warehouse or factory floor is damaged, read our guide to warehouse floor repairs before resin flooring.

Mechanical preparation takes time

Floor preparation should not be treated as an optional stage simply to shorten the programme.

Depending on the substrate and specified system, mechanical preparation such as diamond grinding may be required.

The objective is to create an appropriately prepared surface for the subsequent flooring stages.

Preparation may also reveal defects that were not obvious beforehand.

Where additional repairs become necessary, those need to be dealt with appropriately rather than ignored simply to maintain an unrealistic schedule.

Repairs can change the installation programme

Cracks, holes, worn sections and other defects can affect the amount of preparation required.

The time involved depends on the type and extent of the damage and the repair method appropriate to the project.

A handful of localised defects is very different from widespread deterioration across a large industrial floor.

For businesses working to a strict shutdown period, the existing floor condition should therefore be discussed as early as possible.

The flooring system affects installation time

Not all resin flooring systems have the same number of stages or curing requirements.

A flooring project may involve a different build-up depending on the environment and required performance. Epoxy and polyurethane systems can also have different product and installation requirements.

Rather than assuming one system will always be quicker than another, the programme should be based on the actual specified products and manufacturer’s technical information.

For more information about system selection, read our guide to epoxy vs polyurethane flooring for commercial and industrial environments.

How long does resin flooring take to cure?

There is no single curing time that should be applied to every resin flooring product.

Curing and return-to-service times can vary according to factors including:

  • Product
  • Flooring system
  • Temperature
  • Site conditions
  • Number and type of layers
  • Intended traffic
  • Manufacturer requirements

There can also be a difference between a surface being ready for the next installation stage and being ready for normal operational traffic.

For that reason, Epoxy Guys should not promise a universal number of hours before a commercial floor can be used.

The programme should follow the requirements of the specified system.

When can forklifts go back onto a resin floor?

This needs to be established for the actual flooring system.

The fact that a surface appears dry does not automatically mean it is ready for forklifts, pallet trucks, vehicles or heavy machinery.

Different types of traffic can place very different loads on a newly installed floor.

The appropriate return-to-service period should therefore be determined using the specified system and relevant product guidance.

Businesses should tell the flooring contractor about forklift and vehicle requirements before installation begins so this can be incorporated into project planning.

Can a warehouse stay open during resin flooring installation?

Potentially, depending on the site and flooring system.

Some larger commercial projects may be capable of being organised into sections or phases.

For example, one area may be taken out of operation while other areas remain available.

However, this depends on factors such as:

  • Building layout
  • Access routes
  • Forklift routes
  • Pedestrian routes
  • Preparation equipment
  • Dust control requirements
  • Flooring system
  • Curing requirements
  • Operational safety
  • Ability to isolate working areas

Phased installation should therefore be planned rather than assumed.

What is phased resin flooring installation?

Phased installation means organising the project so different areas are completed at different stages instead of taking the entire floor out of service at once.

For suitable projects, this may help a business manage operational disruption.

However, phasing can introduce its own considerations.

These may include:

  • Additional mobilisation
  • Working boundaries
  • Access management
  • Sequencing
  • Protecting completed areas
  • Maintaining safe operational routes
  • Coordinating other trades or staff

Whether phasing is practical should be assessed during project planning.

What about factories that cannot stop production?

Factories can be particularly sensitive to downtime.

Before flooring work begins, it is useful to establish:

  1. Which areas are essential to production?
  2. Which areas can be isolated?
  3. Where do staff need access?
  4. Where do forklifts or vehicles travel?
  5. Can equipment be moved?
  6. Are there planned shutdown periods?
  7. Are other contractors working on site?
  8. When does each completed area need to return to service?

Providing this information early makes it easier to plan the flooring project around genuine operational requirements.

It is much better to identify these constraints before installation than after an area has already been taken out of service.

Can resin flooring be installed outside normal working hours?

Some commercial projects may have restrictions or requirements relating to working hours.

Whether evening, weekend or other planned working arrangements are practical depends on the project, access, system and site requirements.

Businesses with a particularly limited shutdown window should raise this during the quotation stage.

Do not assume that out-of-hours installation is available or appropriate for every project; it should be agreed as part of the individual project plan.

How can a business reduce unnecessary downtime?

Good planning can make a significant difference.

Before the project begins:

Provide accurate measurements

Accurate floor areas help with material and project planning.

Send photographs early

Photographs can highlight obvious repairs, old coatings and floor condition before further assessment.

Explain how the building operates

Tell the contractor about forklifts, production areas, pedestrian routes, loading bays and essential access.

Discuss shutdown periods

If the business has planned maintenance periods, quieter days or other shutdown windows, mention them during the quotation stage.

Clear the working area

Where agreed as the client’s responsibility, ensuring areas are accessible can prevent avoidable delays.

Agree the specification beforehand

Colours, finish, system requirements and operational considerations should ideally be established before installation starts.

Last-minute specification changes can affect both materials and programme.

Does faster always mean better?

No.

Reducing unnecessary downtime is important, but preparation, repair, application and curing requirements should not be skipped simply to make a programme look faster.

The objective is to plan the project efficiently while still following the requirements of the specified flooring system.

A commercial flooring programme should therefore be realistic rather than based on the shortest possible headline time.

How does installation time affect commercial resin flooring cost?

Programme and cost can sometimes be connected.

For example, access restrictions, phasing or specific operational requirements may change how labour and installation need to be organised.

However, floor condition, preparation and system choice also affect the overall quotation.

For a fuller breakdown, read our guide to commercial resin flooring costs in the UK.

What should I send Epoxy Guys when planning around downtime?

For an initial commercial flooring enquiry, provide:

  1. Approximate floor area in m²
  2. Project location
  3. Photographs of the existing floor
  4. What the building is used for
  5. Existing floor condition
  6. Forklift, pallet truck or vehicle requirements
  7. Machinery or production requirements
  8. Essential access routes
  9. Available shutdown periods
  10. Preferred project timeframe

For larger or more complex commercial sites, further assessment may be required before the final specification and programme are confirmed.

Planning warehouse or factory flooring around your operation?

Commercial flooring is not only about choosing the finished surface.

The installation needs to work around the building, the flooring system and the business using it.

Epoxy Guys can assess the floor, operational requirements and proposed resin system to help establish an appropriate project plan. Our guide to epoxy resin flooring for factories and warehouses covers system selection in more detail, alongside our commercial and industrial flooring hub.

Discuss your commercial flooring project

Need to plan resin flooring around warehouse or factory operations? Tell us about your floor, site and available downtime.